To ensure safe, efficient, and reliable travel for motorists that use the more than 1,700 miles of roads and 225 bridges under the jurisdiction of Macomb County, MDCR is committed to improving our transportation infrastructure by delivering quality road, bridge, and traffic projects.
Between state, county, and local projects, there are hundreds of work zones in Macomb County each year. To help all road users navigate construction work in Macomb County, the Macomb Work Zone includes information and resources to keep the public informed and up to date of what's happening on the roadways.
Sign up to receive real-time lane closure information and construction updates from the Department of Roads.
Work zone safety
MCDR works closely with local contractors and engineers to build some of the safest and most efficient roads in Michigan. To help keep the roads, workers, and drivers safe, MCDR strongly encourages drivers to practice these driving tips:
- Plan ahead. Expect delays, plan for them, and leave early to reach your destination on time. When you can, avoid work zones altogether by using alternate routes.
- Obey road crews and signs. When approaching a work zone, watch for cones, barrels, signs, large vehicles, or workers in bright-colored vests to warn you and direct you where to go.
- Slow down. Look for signs indicating the speed limit through the work zone. Keep a safe distance from the vehicle ahead of you and follow the posted speed limit.
- Move over. Most state move-over laws apply when passing work crews and official vehicles parked on the shoulder with flashing warning lights.
- Avoid distractions. Keep your eyes on the road and off your phone at all times.
- Watch for sudden stoppages. Don’t make sudden lane changes in front of trucks that are trying to slow down.
Active projects
Below is a list of active projects on Macomb County roads.
32 Mile Road and M-53 in Washington Township
Location: Intersection
Traffic: The southbound left lane of M-53 at 32 Mile Road is closed until further notice. Drivers are encouraged to seek alternate routes.
Duration: Spring 2026 – Summer 2026
Description: Work is associated with a sewer infrastructure project by Washington Township. Contact the Washington Township Department of Public Works at 586-786-0012 for additional information.
11 Mile Road in Warren
Location: East of Dequindre Road
Traffic: A double lane closure is in place on northbound Dequindre Road between 11 Mile Road and Edward Griggs Boulevard. A single lane closure is in place on westbound 11 Mile Road between David Givens Street and Dequindre Road.
Duration: March 2026 – October 2026
Description: Eight miles of natural gas pipeline will be replaced in Oakland and Macomb counties. Work is part of the Consumers Energy Four Cities Metro Pipeline project. Contact 248-433-5780 or fourcitiespipeline@cmsenergy.com for additional information.
Powell Road in Washington Township
Location: Between 30-1/2 Mile Road and 32 Mile Road
Traffic: Powell Road will be closed to through traffic between 30 Mile Road and 32 Mile Road. Drivers are encouraged to follow the posted detours on Van Dyke Avenue, M-53 and Romeo Plank Road and to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 6, 2026 – July 2026
Description: Reconstruction.
23 Mile Road and Schoenherr Road in Shelby Township
Location: Intersection
Traffic: Eastbound, westbound and southbound traffic at the intersection of 23 Mile Road and Schoenherr Road will be reduced to one lane in each direction. Drivers are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 13, 2026 – June 2026
Description: Work is associated with a sanitary sewer project by Shelby Township. Contact the Shelby Township Department of Public Works at 586-731-5990 for additional information.
North River Road in Harrison Township
Location: Between I-94 and Bridgeview Street
Traffic: North River Road is open to eastbound traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 13, 2026 – Summer 2026
Description: Road rehabilitation.
Garfield Road in Fraser
Location: Between 14 Mile Road and 15 Mile Road
Traffic: The road is open to traffic. Intermittent lane closures will be in place to perform restoration and punch list work. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 2026 – Summer 2026
Description: Road reconstruction.
14 Mile Road in Clinton Township and Roseville
Location: Between Kelly Road and Gratiot Avenue (M-3)
Traffic: The road is open to traffic. Intermittent lane closures will be in place to perform restoration and punch list work. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 2026 – Summer 2026
Description: Restoration and punch list work.
14 Mile Road in Sterling Heights
Location: Between Van Dyke Avenue (M-53) and Hoover Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 27, 2026 – Summer 2026
Description: Road rehabilitation.
10 Mile Road in Center Line and Warren
Location: Between Ryan Road and Lorraine Avenue
Traffic: The road is open to traffic. Intermittent lane closures will be in place to perform restoration and punch list work. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: May 2026 – Summer 2026
Description: Restoration and punch list work.
Mound Road in Warren
Location: Southbound ramps at I-696
Traffic: The ramps will remain open and traffic will be maintained during construction operations. The southbound service drive will be closed the morning of May 6 for paving operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: May 4, 2026 – June 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Mound Road in Warren
Location: Between M-102 and I-696
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: May 4, 2026 – June 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Iroquois Street in Clinton Township
Location: Between Gratiot Avenue (M-3) and Radde Street
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 7, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Laurel Street in Clinton Township
Location: Between Gratiot Avenue (M-3) and Hardy Street
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 7, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Penrod Drive in Clinton Township
Location: Between Garfield Road and Kelly Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 8, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Bruce Hill Drive in Shelby Township
Location: Between 24 Mile Road and Chapman Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 8, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Grace Street in Shelby Township
Location: Between Van Dyke Avenue and Driftwood Drive
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 8, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Sherwood Lane in Shelby Township
Location: Between 24 Mile Road and 25 Mile Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 8, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Jerome Street in Chesterfield Township
Location: Between Edith Street and Helmandale Street
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 9, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Joel Street in Chesterfield Township
Location: Between Edith Street and Helmandale Street
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 9, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Monte Road in Chesterfield Township
Location: Between Belmont Boulevard and Monmouth Drive
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 9, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Salt River Drive in Chesterfield Township
Location: Between Lakeview Street and Meldrum Street
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: May 9, 2026 – June 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Guardrail Safety Work in Macomb County
Location: Countywide
Traffic: A contractor will perform guardrail work at locations throughout Macomb County. Intermittent lane closures with flagging operations will be in place to control traffic at active project locations. The schedule for each location will vary and weather may affect scheduled work.
Duration: May 11, 2026 – Summer 2026
Description: Guardrail work. Work is part of MCDR's 2026 Guardrail Safety Program.
Dequindre Road in Warren
Location: Between M-102 and Maplelane Avenue
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 1, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Dequindre Road in Warren
Location: Between 13 Mile Road and 14 Mile Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 3, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Moravian Drive in Clinton Township
Location: Between Metropolitan Parkway and Cass Avenue
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 6, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Sugarbush Road in Chesterfield Township
Location: Between Callens Road and Jefferson Avenue
Traffic: Sugarbush Road will be open to northbound traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project. Residents on Sugarbush Road are encouraged to place their trash bins on the north side of the road on waste pickup days.
Duration: June 9, 2026 – September 2026
Description: Road rehabilitation.
Metropolitan Parkway in Sterling Heights
Location: Between Mound Road and M-53
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 11, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Ashbrooke Drive in Shelby Township
Location: Between Hawthorne Drive and Nickelby Drive
Traffic: Ashbrooke Drive will be open to one way traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: June 11, 2026 – July 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Hawthorne Drive in Shelby Township
Location: Between Nickelby Drive and east of Ashbrooke Drive
Traffic: Hawthorne Drive will be open to one way traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: June 11, 2026 – July 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Scarboro Way in Shelby Township 🚧
Location: Between Kingscross Drive and Westcott Court
Traffic: Scarboro Way will be open to one way traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: June 15, 2026 – July 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Susan Road in Macomb Township 🚧
Location: Between 21 Mile Road and Tilch Road
Traffic: Susan Road will be open to one way traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: June 17, 2026 – July 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Jefferson Avenue in Harrison Township 🚧
Location: Between Metropolitan Parkway and South River Road
Traffic: Jefferson Avenue will be open to northbound traffic only. Drivers are encouraged to follow the posted detour and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 22, 2026 – September 2026
Description: Road rehabilitation.
🚧 Canal Road in Clinton Township 🚧
Location: Between Hayes Road and Clinton River Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 23, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Romeo Plank Road in Clinton Township 🚧
Location: Between Clinton River Road and Cass Avenue
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 26, 2026 – July 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 – Indicates new project or updated project information.
All dates are estimated and subject to change. Weather affects all work and may cause delays or cancellations.
2026 planned projects
MCDR has an extensive mix of work and road, bridge and traffic infrastructure improvements planned for 2026. Below is a list of anticipated projects.
Road Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| 26 Mile Road and Hayes Road | Intersection | $1,000,000 | Reconstruction | Macomb Township, Ray Township, Shelby Township and Washington Township |
| 32 Mile Road | CN Railroad Crossing to County Line Road | $621,685 | Preventive maintenance | Richmond and Richmond Township |
| Broughton Road | 23-1/2 Mile Road to 24-1/2 Mile Road | $7,000,000 | Reconstruction | Macomb Township |
| Jefferson Avenue | Metropolitan Parkway to South River Road | $1,387,198 | Rehabilitation | Harrison Township |
| Little Mack Avenue | Tullio Street to South Nunneley Road, Carlier Street and South Nunneley | $2,800,000 | Reconstruction | Clinton Township |
| North River Road | I-94 to Bridgeview Street | $2,363,329 | Rehabilitation | Harrison Township |
| Powell Road | 30-1/2 Mile Road to 32 Mile Road | $5,349,263 | Reconstruction | Washington Township |
| Romeo Plank Road | 28 Mile Road to 29 Mile Road | $629,328 | Preventive maintenance | Ray Township |
| Sugarbush Road | Callens Road to Jefferson Avenue | $1,241,136 | Rehabilitation | Chesterfield Township |
| William P. Rosso Highway | I-94 to Jefferson Avenue | $12,933,963 | Reconstruction | Chesterfield Township and Harrison Township |
| Salt River Drive | Lakeview Street to Meldrum Street | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Sugarbush Road and Callens Road | Peltier Drain to Sass Road | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Sugarbush Road | Cotton Road to Rachid Lane | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Cotton Road | Gratiot Avenue to Halo Drive | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Clinton River Road | Hayes Road to Garfield Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Clinton River Road | Garfield Road to 17 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| 21 Mile Road | Garfield Road to Romeo Plank Road | Pavement Preservation Program (PPP) | Asphalt overlay | Macomb Township |
| Bordman Road | Cryderman Road to Deland Road | Pavement Preservation Program (PPP) | Asphalt overlay | Richmond Township |
| 25 Mile Road | Dequindre Road to Mound Road | Pavement Preservation Program (PPP) | Asphalt overlay | Shelby Township |
| Shelby Road | Olen Street to Utica city limits | Pavement Preservation Program (PPP) | Asphalt overlay | Shelby Township |
| Mound Road southbound ramps | I-696 | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Dequindre Road | 13 Mile Road to 14 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Dequindre Road | M-102 to Maplelane Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| 27 Mile Road | Van Dyke Avenue to Jewell Road | Pavement Preservation Program (PPP) | Asphalt overlay | Washington Township |
| Jewell Road | 28 Mile Road to 29 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Washington Township |
| Canal Road | Hayes Road to Clinton River Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Moravian Drive | Metropolitan Parkway to Cass Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Romeo Plank Road | Clinton River Road to Cass Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Mound Road | M-102 to I-696 | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Metropolitan Parkway | Mound Road to M-53 | Pavement Preservation Program (PPP) | Asphalt overlay | Sterling Heights |
| Aynesley Street | 17 Mile Road to south of Monticello Drive | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Melody Court | At Woodstream Drive | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Rudgate Way | Little Mack Avenue to M-97 | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Avery Street | Crocker Boulevard to South River Road | Pavement Preservation Program (PPP) | Concrete patching | Mount Clemens and Clinton Township |
| Burgess Drive | Entrances | Pavement Preservation Program (PPP) | Concrete patching | Chesterfield Township |
| 14 Mile Road | Hayes Road to Utica Road | Pavement Preservation Program (PPP) | Concrete patching | Fraser |
| Seaway Court | At North Seaway Court | Pavement Preservation Program (PPP) | Concrete patching | Harrison Township |
| Susan Road | 21 Mile Road to Tilch Road | Pavement Preservation Program (PPP) | Concrete patching | Macomb Township |
| Valerie Drive | Hayes Road to Van Meter Drive | Pavement Preservation Program (PPP) | Concrete patching | Macomb Township |
| 10 Mile Road and Little Mack Avenue | Intersection | Pavement Preservation Program (PPP) | Concrete patching | St. Clair Shores |
| Ashbrooke Drive | Hawthorne Drive to Nickelby Drive | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Hawthorne Drive and Ashbrooke Drive | Creekside Village | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Scarboro Way | Kingscross Drive and Westcott Court | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Schoenherr Road | M-59 to 21 Mile Road | Pavement Preservation Program (PPP) | Concrete patching | Utica and Shelby Township |
| 10 Mile Road | Lorraine Avenue to Hoover Road | Pavement Preservation Program (PPP) | Concrete patching | Warren |
| Crack Sealing Program | Countywide | $500,000 | Pavement preservation | Macomb County |
Bridge and Culvert Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| 21 Mile Road | Over the Salt Slang Gloede Drain | $5,120,000 | Bridge replacement | Macomb Township |
| Jefferson Avenue | Over the Clinton River Spillway | $862,000 | Preventive maintenance | Harrison Township |
| Romeo Plank Road | Over the Newland Drain | $1,857,000 | Bridge replacement | Armada Township |
| Schoenherr Road | Over the Red Run Drain | $6,264,882 | Deck replacement | Sterling Heights |
Subdivision Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Annsbury Drive | Van Dyke Avenue to Baypoint Drive | $1,185,527 | Subdivision reconstruction | Shelby Township |
| Bittersweet Lane and Country Club Drive | Shelby Road to Sandy Creek Drive | $655,051 | Subdivision reconstruction | Shelby Township |
| Cedarview | Christopher Court, Saxon Drive and Brookhill Drive | $1,297,805 | Subdivision reconstruction | Bruce Township |
| Fieldcrest | Vincent Trail to East Nocturne Lane | $776,032 | Subdivision reconstruction | Shelby Township |
| Nautical Drive | Lotties Drive to dead end | $674,730 | Subdivision reconstruction | Chesterfield Township |
| Beaconsfield Street | 14 Mile Road to Gaynon Drive | $190,000 | Subdivision preservation | Clinton Township |
| Bruce Hill Drive | 24 Mile Road to Chapman Road | $135,360 | Subdivision preservation | Shelby Township |
| Glenwood Street | M-3 to Harper Avenue | $487,000 | Subdivision preservation | Clinton Township |
| Grace Street | Van Dyke Avenue to Driftwood Drive | $112,320 | Subdivision preservation | Shelby Township |
| Iroquois Street | M-3 to Radde Street | $103,680 | Subdivision preservation | Clinton Township |
| Jerome Street | Edith Street to Helmandale Street | $100,800 | Subdivision preservation | Chesterfield Township |
| Joel Street | Edith Street to Helmandale Street | $95,040 | Subdivision preservation | Chesterfield Township |
| Laurel Street | M-3 to Hardy Street | $123,840 | Subdivision preservation | Clinton Township |
| Little Mack Avenue | 14 Mile Road to McKishnie Street | $159,000 | Subdivision preservation | Clinton Township |
| Mallast Street | Jefferson Avenue to Wall Street | $120,960 | Subdivision preservation | Harrison Township |
| Monte Road | Belmont Boulevard to Monmouth Drive | $51,840 | Subdivision preservation | Chesterfield Township |
| Penrod Drive | Garfield Road to Kelly Road | $305,000 | Subdivision preservation | Clinton Township |
| Ponchartrain Street | Acacia Street to Jefferson Avenue | $106,560 | Subdivision preservation | Harrison Township |
| Sherwood Lane | 24 Mile Road to 25 Mile Road | $345,600 | Subdivision preservation | Shelby Township |
| Shoreline Drive | South River Road to dead end | $213,120 | Subdivision preservation | Harrison Township |
Non-Motorized Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Bonior Trail Pathway Improvements | Non-motorized pathway | $2,103,726 | Non-motorized | Clinton Township |
| Clinton River Spillway Trail (Shady Side Park) Pathway Improvements | Non-motorized pathway | $728,635 | Non-motorized | Clinton Township |
| Jefferson Avenue Pathway | Non-motorized pathway | $919,700 | Non-motorized | Chesterfield Township |
| Jefferson Avenue Spillway Pedestrian Bridge | Non-motorized pathway | $3,977,917 | Non-motorized | Harrison Township |
| 25 Mile Road Pedestrian Bridge | Non-motorized pathway | $1,300,000 | Non-motorized | Shelby Township |
Anticipated projects are subject to change.
2027 planned projects
MCDR has an extensive mix of work and road, bridge and traffic infrastructure improvements planned for 2027. Below is a list of anticipated projects.
Road Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Romeo Plank Road | 21-1/2 Mile Road to 23 Mile Road | $16,500,000 | Reconstruction | Macomb Township |
| Schoenherr Road | 23 Mile Road to 25 Mile Road | $9,237,762 | Reconstruction | Shelby Township |
| 12 Mile Road | Utica Road to I-94 | $3,045,642 | Rehabilitation | Roseville |
| 21 Mile Road and Heydenreich Road | Intersection | $7,404,821 | Reconstruction | Macomb Township |
| Mound Road | 29 Mile Road to 32 Mile Road | $1,810,403 | Preventive maintenance | Washington Township |
| Romeo Plank Road | 29 Mile Road to 30 Mile Road | $500,000 | Preventive maintenance | Ray Township |
| Hayes Road | 23 Mile Road to 25 Mile Road | $2,820,653 | Preventive maintenance | Macomb Township and Shelby Township |
| Jefferson Avenue | Rosso Highway to Altman Road | $6,001,693 | Preventive maintenance | Chesterfield Township |
| Jefferson Avenue | Altman Road to 23 Mile Road | Preventive maintenance | New Baltimore | |
| Harrington Street | M-97 to Hilldale Street | $3,000,000 | Reconstruction | Clinton Township and Mt. Clemens |
| M-19 and 26 Mile Road | Intersection | $1,000,000 | Rehabilitation | Chesterfield Township and New Haven |
| Henry B. Joy Boulevard | M-3 to Irwin Road | $5,322,541 | Reconstruction | Clinton Township, Harrison Township and Mt. Clemens |
| Asphalt Pavement Preservation Program | Countywide | $8,000,000 | Pavement preservation | Macomb County |
| Concrete Pavement Preservation Program | Countywide | $8,000,000 | Pavement preservation | Macomb County |
| Crack Sealing Program | Countywide | $500,000 | Pavement preservation | Macomb County |
Bridge and Culvert Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Hayes Road | Over the Middle Branch Clinton River | $604,000 | Preventive maintenance | Macomb Township and Shelby Township |
| Moravian Drive | Over the Clinton River | $309,000 | Preventive maintenance | Clinton Township |
| Westbound Metropolitan Parkway | Over the Harrington Drain | $140,000 | Preventive maintenance | Clinton Township |
| Eeastbound Metropolitan Parkway | Over the Harrington Drain | $140,000 | Preventive maintenance | Clinton Township |
| North Avenue | Over the East Branch Coon Creek | $2,993,000 | Bridge replacement | Ray Township |
| North River Road | Over the Catfish Channel | $5,057,904 | Bridge replacement | Harrison Township |
| Romeo Plank Road | Over the Newland Drain | $1,857,000 | Bridge replacement | Armada Township |
| 28 Mile Road | Over the Ray and Lenox Drain | $150,000 | Culvert replacement | Lenox Township |
| Armada Ridge Road | Over the Salt River | $150,000 | Culvert replacement | Richmond Township |
Subdivision Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Subdivision Reconstruction Program | Countywide | $5,000,000 | Subdivision reconstruction | Macomb County |
| Subdivision Preservation Program | Countywide | $1,250,000 | Subdivision reconstruction | Macomb County |
Anticipated projects are subject to change.