To ensure safe, efficient, and reliable travel for motorists that use the more than 1,700 miles of roads and 225 bridges under the jurisdiction of Macomb County, MDCR is committed to improving our transportation infrastructure by delivering quality road, bridge, and traffic projects.
Between state, county, and local projects, there are hundreds of work zones in Macomb County each year. To help all road users navigate construction work in Macomb County, the Macomb Work Zone includes information and resources to keep the public informed and up to date of what's happening on the roadways.
Sign up to receive real-time lane closure information and construction updates from the Department of Roads.
Work zone safety
MCDR works closely with local contractors and engineers to build some of the safest and most efficient roads in Michigan. To help keep the roads, workers, and drivers safe, MCDR strongly encourages drivers to practice these driving tips:
- Plan ahead. Expect delays, plan for them, and leave early to reach your destination on time. When you can, avoid work zones altogether by using alternate routes.
- Obey road crews and signs. When approaching a work zone, watch for cones, barrels, signs, large vehicles, or workers in bright-colored vests to warn you and direct you where to go.
- Slow down. Look for signs indicating the speed limit through the work zone. Keep a safe distance from the vehicle ahead of you and follow the posted speed limit.
- Move over. Most state move-over laws apply when passing work crews and official vehicles parked on the shoulder with flashing warning lights.
- Avoid distractions. Keep your eyes on the road and off your phone at all times.
- Watch for sudden stoppages. Don’t make sudden lane changes in front of trucks that are trying to slow down.
Active projects
Below is a list of active projects on Macomb County roads.
11 Mile Road in Warren
Location: East of Dequindre Road
Traffic: A double lane closure is in place on northbound Dequindre Road between 11 Mile Road and Edward Griggs Boulevard. A single lane closure is in place on westbound 11 Mile Road between David Givens Street and Dequindre Road.
Duration: March 2026 – October 2026
Description: Eight miles of natural gas pipeline will be replaced in Oakland and Macomb counties. Work is part of the Consumers Energy Four Cities Metro Pipeline project. Contact 248-433-5780 or fourcitiespipeline@cmsenergy.com for additional information.
14 Mile Road in Clinton Township and Roseville
Location: Between Kelly Road and Gratiot Avenue (M-3)
Traffic: The road is open to traffic. Intermittent lane closures will be in place to perform restoration and punch list work. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: April 2026 – Summer 2026
Description: Restoration and punch list work.
Guardrail Safety Work in Macomb County
Location: Countywide
Traffic: A contractor will perform guardrail work at locations throughout Macomb County. Intermittent lane closures with flagging operations will be in place to control traffic at active project locations. The schedule for each location will vary and weather may affect scheduled work.
Duration: May 11, 2026 – Summer 2026
Description: Guardrail work. Work is part of MCDR's 2026 Guardrail Safety Program.
Sugarbush Road in Chesterfield Township
Location: Between Callens Road and Jefferson Avenue
Traffic: Sugarbush Road will be open to northbound traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 9, 2026 – September 2026
Description: Road rehabilitation.
Jefferson Avenue in Harrison Township
Location: Between Metropolitan Parkway and South River Road
Traffic: Jefferson Avenue will be open to northbound traffic only. Drivers are encouraged to follow the posted detour and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: June 22, 2026 – September 2026
Description: Road rehabilitation.
Schoenherr Road over the Red Run Drain in Sterling Heights
Location: Between 15 Mile Road and Moravian Drive
Traffic: Schoenherr Road will be partially open during bridge work with two temporary lanes of traffic. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: July 6, 2026 – November 2026
Description: Bridge deck replacement.
Broughton Road in Macomb Township
Location: Between 23-1/2 Mile Road to 24-1/2 Mile Road
Traffic: 24 Mile Road will be closed to through traffic between Romeo Plank Road and Foss Road. Drivers are encouraged to follow the posted detour and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: July 9, 2026 – November 2026
Description: Road reconstruction.
Glenwood Street in Clinton Township
Location: Between M-3 and Harper Avenue
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: July 15, 2026 – August 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
Iroquois Street in Clinton Township
Location: Between northbound M-3 and southbound M-3
Traffic: The road will remain open and traffic will be maintained during construction operations. Access to all properties will be maintained throughout the duration of the project.
Duration: July 15, 2026 – August 2026
Description: Road resurfacing. The project is part of MCDR's 2026 Subdivision Preservation Program (SPP).
25 Mile Road in Shelby Township
Location: Between Dequindre Road and Mound Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: July 16, 2026 – August 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Aynesley Street in Clinton Township
Location: Between 17 Mile Road and south of Monticello Drive
Traffic: Aynesley Street will be open to one way traffic only. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: July 27, 2026 – August 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
21 Mile Road in Macomb Township
Location: Between Garfield Road and Romeo Plank Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: July 27, 2026 – August 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Romeo Plank Road in Clinton Township
Location: Between Clinton River Road and Cass Avenue
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: July 27, 2026 – August 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Pavement Marking in Macomb County
Location: Countywide
Traffic: A contractor will be performing pavement line painting work throughout Macomb County. Moving lane closures will be in place during painting operations and painting crews will be working multiple days per week, including weekends. The schedule for each road may vary and weather may affect scheduled work.
Duration: July 27, 2026 – September 2026
Description: Pavement marking painting. Work is part of MCDR's 2026 Longitudinal Pavement Marking Program.
Melody Court in Clinton Township
Location: At Woodstream Drive
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: August 4, 2026 – September 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
Avery Street in Clinton Township and Mount Clemens
Location: Between Crocker Boulevard and South River Road
Traffic: Southbound Avery Street will be closed to through traffic during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: August 7, 2026 – September 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Canal Road in Clinton Township 🚧
Location: Between Hayes Road and Clinton River Road
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: August 10, 2026 – September 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Bonior Trail in Clinton Township 🚧
Location: Between Utica Road and the Clinton River
Traffic: Intermittent closures of sections of the Bonior Trail will be in place during rehabilitation operations.
Duration: August 10, 2026 – Fall 2026
Description: Trail and pedestrian bridge rehabilitation. Work is associated with Bonior Trail pathway improvements by Clinton Township. Contact the Clinton Township Department of Public Services at 586-286-9300 for additional information.
🚧 Cotton Road in Chesterfield Township 🚧
Location: Between Gratiot Avenue (M-3) and Halo Drive
Traffic: The road will remain open and traffic will be maintained during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: August 17, 2026 – September 2026
Description: Asphalt preservation and resurfacing. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 Little Mack Avenue, Carlier Street and South Nunneley Road in Clinton Township 🚧
Location: Between Groesbeck Highway and Gratiot Avenue
Traffic: Little Mack Avenue, Carlier Street and South Nunneley Road will be open to local traffic only. Drivers should expect delays and are encouraged to seek alternate routes. Access to all properties will be maintained throughout the duration of the project, but through traffic will be restricted.
Duration: August 17, 2026 – November 2026
Description: Road reconstruction.
🚧 14 Mile Road in Fraser 🚧
Location: Between Hayes Road and Utica Road
Traffic: The road will remain open with lane closures in place during construction operations. Drivers should expect delays and are encouraged to seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: August 17, 2026 – September 2026
Description: Concrete patching. The project is part of MCDR's 2026 Pavement Preservation Program (PPP).
🚧 32 Mile Road in Richmond and Richmond Township 🚧
Location: Between the CN railroad crossing and the County line
Traffic: The road will be open to one way traffic during construction operations. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all businesses and properties will be maintained throughout the duration of the project.
Duration: August 31, 2026 – October 2026
Description: Asphalt preventive maintenance and resurfacing.
🚧 Utica Road railroad crossing in Fraser 🚧
Location: Between Groesbeck Highway (M-97) and Masonic
Traffic: The railroad crossing is anticipated to be closed September 14 through September 20 for railroad repair work. Utica Road will be closed to through traffic at the railroad crossing. Drivers are encouraged to follow the posted detours and seek alternate routes. Access to all properties will be maintained throughout the duration of the project.
Duration: September 14, 2026 – September 20, 2026
Description: The closure is associated with railroad crossing repair work by CN Railway.
🚧 – Indicates new project or updated project information.
All dates are estimated and subject to change. Weather affects all work and may cause delays or cancellations.
2026 planned projects
MCDR has an extensive mix of work and road, bridge and traffic infrastructure improvements planned for 2026. Below is a list of anticipated projects.
Road Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| 26 Mile Road and Hayes Road | Intersection | $1,000,000 | Reconstruction | Macomb Township, Ray Township, Shelby Township and Washington Township |
| 32 Mile Road | CN Railroad Crossing to the County line | $621,685 | Preventive maintenance | Richmond and Richmond Township |
| Broughton Road | 23-1/2 Mile Road to 24-1/2 Mile Road | $7,000,000 | Reconstruction | Macomb Township |
| Jefferson Avenue | Metropolitan Parkway to South River Road | $1,387,198 | Rehabilitation | Harrison Township |
| Little Mack Avenue | Tullio Street to South Nunneley Road, Carlier Street and South Nunneley | $2,800,000 | Reconstruction | Clinton Township |
| North River Road | I-94 to Bridgeview Street | $2,363,329 | Rehabilitation | Harrison Township |
| Powell Road | 30-1/2 Mile Road to 32 Mile Road | $5,349,263 | Reconstruction | Washington Township |
| Romeo Plank Road | 28 Mile Road to 29 Mile Road | $629,328 | Preventive maintenance | Ray Township |
| Sugarbush Road | Callens Road to Jefferson Avenue | $1,241,136 | Rehabilitation | Chesterfield Township |
| William P. Rosso Highway | I-94 to Jefferson Avenue | $12,933,963 | Reconstruction | Chesterfield Township and Harrison Township |
| Salt River Drive | Lakeview Street to Meldrum Street | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Sugarbush Road and Callens Road | Peltier Drain to Sass Road | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Sugarbush Road | Cotton Road to Rachid Lane | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Cotton Road | Gratiot Avenue to Halo Drive | Pavement Preservation Program (PPP) | Asphalt overlay | Chesterfield Township |
| Clinton River Road | Hayes Road to Garfield Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Clinton River Road | Garfield Road to 17 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| 21 Mile Road | Garfield Road to Romeo Plank Road | Pavement Preservation Program (PPP) | Asphalt overlay | Macomb Township |
| Bordman Road | Cryderman Road to Deland Road | Pavement Preservation Program (PPP) | Asphalt overlay | Richmond Township |
| 25 Mile Road | Dequindre Road to Mound Road | Pavement Preservation Program (PPP) | Asphalt overlay | Shelby Township |
| Shelby Road | Olen Street to Utica city limits | Pavement Preservation Program (PPP) | Asphalt overlay | Shelby Township |
| Mound Road southbound ramps | I-696 | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Dequindre Road | 13 Mile Road to 14 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Dequindre Road | M-102 to Maplelane Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| 27 Mile Road | Van Dyke Avenue to Jewell Road | Pavement Preservation Program (PPP) | Asphalt overlay | Washington Township |
| Jewell Road | 28 Mile Road to 29 Mile Road | Pavement Preservation Program (PPP) | Asphalt overlay | Washington Township |
| Canal Road | Hayes Road to Clinton River Road | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Moravian Drive | Metropolitan Parkway to Cass Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Romeo Plank Road | Clinton River Road to Cass Avenue | Pavement Preservation Program (PPP) | Asphalt overlay | Clinton Township |
| Mound Road | M-102 to I-696 | Pavement Preservation Program (PPP) | Asphalt overlay | Warren |
| Metropolitan Parkway | Mound Road to M-53 | Pavement Preservation Program (PPP) | Asphalt overlay | Sterling Heights |
| Aynesley Street | 17 Mile Road to south of Monticello Drive | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Melody Court | At Woodstream Drive | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Rudgate Way | Little Mack Avenue to M-97 | Pavement Preservation Program (PPP) | Concrete patching | Clinton Township |
| Avery Street | Crocker Boulevard to South River Road | Pavement Preservation Program (PPP) | Concrete patching | Mount Clemens and Clinton Township |
| Burgess Drive | Entrances | Pavement Preservation Program (PPP) | Concrete patching | Chesterfield Township |
| 14 Mile Road | Hayes Road to Utica Road | Pavement Preservation Program (PPP) | Concrete patching | Fraser |
| Seaway Court | At North Seaway Court | Pavement Preservation Program (PPP) | Concrete patching | Harrison Township |
| Susan Road | 21 Mile Road to Tilch Road | Pavement Preservation Program (PPP) | Concrete patching | Macomb Township |
| Valerie Drive | Hayes Road to Van Meter Drive | Pavement Preservation Program (PPP) | Concrete patching | Macomb Township |
| 10 Mile Road and Little Mack Avenue | Intersection | Pavement Preservation Program (PPP) | Concrete patching | St. Clair Shores |
| Ashbrooke Drive | Hawthorne Drive to Nickelby Drive | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Hawthorne Drive and Ashbrooke Drive | Creekside Village | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Scarboro Way | Kingscross Drive and Westcott Court | Pavement Preservation Program (PPP) | Concrete patching | Shelby Township |
| Schoenherr Road | M-59 to 21 Mile Road | Pavement Preservation Program (PPP) | Concrete patching | Utica and Shelby Township |
| 10 Mile Road | Lorraine Avenue to Hoover Road | Pavement Preservation Program (PPP) | Concrete patching | Warren |
| Crack Sealing Program | Countywide | $500,000 | Pavement preservation | Macomb County |
Bridge and Culvert Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| 21 Mile Road | Over the Salt Slang Gloede Drain | $5,120,000 | Bridge replacement | Macomb Township |
| Jefferson Avenue | Over the Clinton River Spillway | $862,000 | Preventive maintenance | Harrison Township |
| Romeo Plank Road | Over the Newland Drain | $1,857,000 | Bridge replacement | Armada Township |
| Schoenherr Road | Over the Red Run Drain | $6,264,882 | Deck replacement | Sterling Heights |
Subdivision Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Annsbury Drive | Van Dyke Avenue to Baypoint Drive | $1,185,527 | Subdivision reconstruction | Shelby Township |
| Bittersweet Lane and Country Club Drive | Shelby Road to Sandy Creek Drive | $655,051 | Subdivision reconstruction | Shelby Township |
| Cedarview | Christopher Court, Saxon Drive and Brookhill Drive | $1,297,805 | Subdivision reconstruction | Bruce Township |
| Fieldcrest | Vincent Trail to East Nocturne Lane | $776,032 | Subdivision reconstruction | Shelby Township |
| Nautical Drive | Lotties Drive to dead end | $674,730 | Subdivision reconstruction | Chesterfield Township |
| Beaconsfield Street | 14 Mile Road to Gaynon Drive | $190,000 | Subdivision preservation | Clinton Township |
| Bruce Hill Drive | 24 Mile Road to Chapman Road | $135,360 | Subdivision preservation | Shelby Township |
| Glenwood Street | M-3 to Harper Avenue | $487,000 | Subdivision preservation | Clinton Township |
| Grace Street | Van Dyke Avenue to Driftwood Drive | $112,320 | Subdivision preservation | Shelby Township |
| Iroquois Street | M-3 to Radde Street | $103,680 | Subdivision preservation | Clinton Township |
| Jerome Street | Edith Street to Helmandale Street | $100,800 | Subdivision preservation | Chesterfield Township |
| Joel Street | Edith Street to Helmandale Street | $95,040 | Subdivision preservation | Chesterfield Township |
| Laurel Street | M-3 to Hardy Street | $123,840 | Subdivision preservation | Clinton Township |
| Little Mack Avenue | 14 Mile Road to McKishnie Street | $159,000 | Subdivision preservation | Clinton Township |
| Mallast Street | Jefferson Avenue to Wall Street | $120,960 | Subdivision preservation | Harrison Township |
| Monte Road | Belmont Boulevard to Monmouth Drive | $51,840 | Subdivision preservation | Chesterfield Township |
| Penrod Drive | Garfield Road to Kelly Road | $305,000 | Subdivision preservation | Clinton Township |
| Ponchartrain Street | Acacia Street to Jefferson Avenue | $106,560 | Subdivision preservation | Harrison Township |
| Sherwood Lane | 24 Mile Road to 25 Mile Road | $345,600 | Subdivision preservation | Shelby Township |
| Shoreline Drive | South River Road to dead end | $213,120 | Subdivision preservation | Harrison Township |
Non-Motorized Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Bonior Trail Pathway Improvements | Non-motorized pathway | $2,103,726 | Non-motorized | Clinton Township |
| Clinton River Spillway Trail (Shady Side Park) Pathway Improvements | Non-motorized pathway | $728,635 | Non-motorized | Clinton Township |
| Jefferson Avenue Pathway | Non-motorized pathway | $919,700 | Non-motorized | Chesterfield Township |
| Jefferson Avenue Spillway Pedestrian Bridge | Non-motorized pathway | $3,977,917 | Non-motorized | Harrison Township |
| 25 Mile Road Pedestrian Bridge | Non-motorized pathway | $1,300,000 | Non-motorized | Shelby Township |
Anticipated projects are subject to change.
2027 planned projects
MCDR has an extensive mix of work and road, bridge and traffic infrastructure improvements planned for 2027. Below is a list of anticipated projects.
Road Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Romeo Plank Road | 21-1/2 Mile Road to 23 Mile Road | $16,500,000 | Reconstruction | Macomb Township |
| Schoenherr Road | 23 Mile Road to 25 Mile Road | $9,237,762 | Reconstruction | Shelby Township |
| 12 Mile Road | Utica Road to I-94 | $3,045,642 | Rehabilitation | Roseville |
| 21 Mile Road and Heydenreich Road | Intersection | $7,404,821 | Reconstruction | Macomb Township |
| Mound Road | 29 Mile Road to 32 Mile Road | $1,810,403 | Preventive maintenance | Washington Township |
| Romeo Plank Road | 29 Mile Road to 30 Mile Road | $500,000 | Preventive maintenance | Ray Township |
| Hayes Road | 23 Mile Road to 25 Mile Road | $2,820,653 | Preventive maintenance | Macomb Township and Shelby Township |
| Jefferson Avenue | Rosso Highway to Altman Road | $6,001,693 | Preventive maintenance | Chesterfield Township |
| Jefferson Avenue | Altman Road to 23 Mile Road | Preventive maintenance | New Baltimore | |
| Harrington Street | M-97 to Hilldale Street | $3,000,000 | Reconstruction | Clinton Township and Mt. Clemens |
| M-19 and 26 Mile Road | Intersection | $1,000,000 | Rehabilitation | Chesterfield Township and New Haven |
| Henry B. Joy Boulevard | M-3 to Irwin Road | $5,322,541 | Reconstruction | Clinton Township, Harrison Township and Mt. Clemens |
| Asphalt Pavement Preservation Program | Countywide | $8,000,000 | Pavement preservation | Macomb County |
| Concrete Pavement Preservation Program | Countywide | $8,000,000 | Pavement preservation | Macomb County |
| Crack Sealing Program | Countywide | $500,000 | Pavement preservation | Macomb County |
Bridge and Culvert Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Hayes Road | Over the Middle Branch Clinton River | $604,000 | Preventive maintenance | Macomb Township and Shelby Township |
| Moravian Drive | Over the Clinton River | $309,000 | Preventive maintenance | Clinton Township |
| Westbound Metropolitan Parkway | Over the Harrington Drain | $140,000 | Preventive maintenance | Clinton Township |
| Eeastbound Metropolitan Parkway | Over the Harrington Drain | $140,000 | Preventive maintenance | Clinton Township |
| North Avenue | Over the East Branch Coon Creek | $2,993,000 | Bridge replacement | Ray Township |
| North River Road | Over the Catfish Channel | $5,057,904 | Bridge replacement | Harrison Township |
| Romeo Plank Road | Over the Newland Drain | $1,857,000 | Bridge replacement | Armada Township |
| 28 Mile Road | Over the Ray and Lenox Drain | $150,000 | Culvert replacement | Lenox Township |
| Armada Ridge Road | Over the Salt River | $150,000 | Culvert replacement | Richmond Township |
Subdivision Projects | ||||
| Project | Location | Estimated Cost | Type of Work | Community |
| Subdivision Reconstruction Program | Countywide | $5,000,000 | Subdivision reconstruction | Macomb County |
| Subdivision Preservation Program | Countywide | $1,250,000 | Subdivision reconstruction | Macomb County |
Anticipated projects are subject to change.