Deterioration of large Macomb County sanitary sewer forces critical repair

A critical underground infrastructure project is underway in Macomb County to prevent the collapse of a major sewer in a system that carries raw sewage from approximately 500,000 county residents.

The rehabilitation of an approximately 1 ½-mile-long section of the 15 Mile Interceptor is needed because of severe degradation of the steel-reinforced concrete pipe caused by corrosive sewer gas.

“We’ve lost an inch-and-a-half of the concrete pipe. It’s just eaten away,” said Macomb County Public Works Commissioner Candice S. Miller, whose department initiated the project to prevent a major sinkhole like the one that occurred on 15 Mile Road in Fraser in 2016. “If you don’t get ahead of it, you’re going to have another sinkhole. That’s what happens.”

The $11.5 million project includes the lining of the 5-foot-diameter pipe along 15 Mile -- from two blocks east of Gratiot Avenue to just west of Groesbeck Highway in Clinton Township -- and 268 vertical feet of manhole risers. It includes a steel-ribbed, PVC spiral-wound liner being installed along the inside wall of the pipe.

Last fall, inspections of that portion of the 15 Mile Interceptor by the Public Works Office’s combined use of an underground drone with artificial intelligence analysis of video footage revealed that degradation of the sewer had proceeded faster than expected from a previous inspection. The deterioration of the concrete is caused by hydrogen sulfide, a dangerous gas created by turbulence of sanitary sewage flowing in the pipe.

The underground construction project is scheduled to be completed by January 2027, weather permitting. It will not result in a sewer rate increase. The product is expected to last at least 50 years.

A close-up view of an open manhole at a roadway construction site. A long gray flexible liner or conduit is being fed downward into the circular manhole opening, curving as it descends into the dark underground space. Yellow safety barriers and chains partially surround the work area, and the asphalt surface around the manhole shows signs of active utility construction.

The 15 Mile Interceptor is part of the large Macomb Interceptor Drain Drainage District, serving residents in 11 of Macomb County’s communities.

A utility worker wearing a blue hard hat with a headlamp, a high-visibility safety vest, yellow waterproof sleeves, and protective gloves crouches inside a large corrugated pipe. The worker stands in shallow water while handling several gray liner strips or conduit sections during an underground installation process. The pipe’s ribbed interior curves around the worker, and the headlamp illuminates the confined workspace.

The innovative, spiral wound method requires less construction space on the surface than some other sewer rehabilitation methods. The interlocking PVC strip – measuring approximately 3 inches in width -- is fed from its spool and down a manhole to reach the interior of the interceptor, where workers guide it by hand into a unique tool resembling a bicycle sprocket that presses the liner up against the interior wall of the pipe as the device turns and locks it in place. The flow inside the interceptor is low enough that the contractor’s crew can work inside the pipe while flow continues with less need for a costly sewage bypass system on the ground.

A large blue industrial cable reel stands beside a roadway at an active construction site. Several long gray conduit or cable sections feed through the center of the reel and extend along the ground. In the foreground, a yellow safety barrier with a warning sign surrounds part of the work area.

In Michigan, the spiral wound method was used for the first time by the Macomb County Public Works Office in 2023 to protect the interior of a 755-foot section of the 7-foot-diameter Garfield Interceptor Sewer, beneath Garfield Road at 21 Mile Road in Macomb Township from further corrosion. Prior to the rehabilitation, that section was also shown to have severe degradation of the concrete. Following its completion, the spiral PVC installation was subsequently used in another area of the MIDDD system along 15 Mile Road from just west of Groesbeck, to west of Kelly Road.

“Underground infrastructure may seem out of sight, but it can’t be out of mind, and it certainly isn’t in our department,” Miller said. “There’s nothing magical about this -- you’ve got to make sure you inspect your underground and put together a capital improvement plan.”

Interior view of a large underground sewer or drainage tunnel showing significant structural deterioration. The tunnel wall contains a circular pipe opening surrounded by heavy mineral deposits, staining, and corrosion. A large mound of accumulated debris or hardened sediment extends from the opening
Department:Public Works