FOR IMMEDIATE RELEASE
March 21, 2023
MORE THAN $163 MILLION IN ROAD, BRIDGE, AND TRAFFIC IMPROVEMENTS PLANNED IN MACOMB COUNTY
MOUNT CLEMENS, Mich. – The Macomb County Department of Roads (MCDR) announced plans for the 2023 construction season, which includes more than $163 million in reconstruction, rehabilitation, and infrastructure improvements throughout Macomb County.
“From major reconstruction and rehabilitation to enhancing the safety and efficiency of our roadways, these projects are critical to the transportation infrastructure needs of our region,” said Macomb County Executive Mark A. Hackel. “There isn’t a road or bridge we can’t fix if we have adequate funding. We will continue to advocate for additional state and federal funding to ensure the more than $2 billion dollars in road improvements needed across Macomb County are resolved."
The construction program includes 20 primary and local road projects and five bridges and culverts, in addition to more than 20 asphalt resurfacing and concrete pavement repair projects as part of MCDR’s county-wide pavement preservation program. Work planned includes five township residential streets as part of MCDR’s subdivision reconstruction program, which provides funding assistance to townships for residential and subdivision roads.
The Department of Roads also has multiple maintenance projects, traffic improvement projects, and traffic technology and communication network modernizations planned for this year.
“The Department of Roads takes a comprehensive and strategic approach to managing Macomb County’s transportation network,” said MCDR Director Bryan Santo. “Through a mix of preventative maintenance, rehabilitation, reconstruction work, and traffic improvements, Macomb County will see significant work this year that will strengthen and enhance our roads, bridges, and transportation infrastructure.”
To help Macomb County motorists and road users navigate local construction work, MCDR launched the Macomb Work Zone – a weekly email built to keep motorists informed and up to date of what's happening on the roadways. To sign up for Department of Roads lane closures and construction updates, click here.
Below is a list of primary and local road, bridge and traffic projects that are planned for 2023. All estimated dates are tentative and subject to change. The estimated construction cost for each project includes materials, labor, and equipment required to build or repair infrastructure.
Project |
Location |
Estimated Construction Cost |
Type of Work |
Community |
Estimated Start |
Estimated Finish |
23 Mile Road |
Card Road to Romeo Plank Road |
$15,583,795 |
Widening from 2 to 5 Lanes |
Macomb Township |
June 2022 |
Fall 2023 |
14 Mile Road |
Hayes Road to Hoover Road |
$6,523,820 |
Mill, Base Repair, and Asphalt Overlay |
Sterling Heights and Warren |
Spring 2023 |
Summer 2023 |
28 Mile Road Bridge |
Over the Deer Creek |
MDOT Bridge Bundle Program |
Bridge Removal |
Lenox Township |
Fall 2023 |
Fall 2023 |
30 Mile Road |
Mound Road to Bur Oak Drive |
Permit Project by Washington Township |
Gravel to Asphalt Road |
Washington Township |
Spring 2023 |
Summer 2023 |
30 Mile Road |
Bur Oak Drive to Kildare Drive |
$2,348,167 |
Gravel to Asphalt Road |
Washington Township |
Summer 2023 |
Fall 2023 |
33 Mile Road |
Lowe Plank Road to Main Street (M-19) |
$555,199 |
Asphalt Overlay |
Richmond |
Summer 2023 |
Summer 2023 |
Campground Road |
Van Dyke Avenue to 28 Mile Road |
$3,000,000 |
Road Rehabilitation, Culvert Replacement, and Roundabout Construction |
Washington Township |
Summer 2023 |
Fall 2023 |
Capac Road |
Irwin Road to Pratt Road |
$871,083 |
Asphalt Overlay |
Armada Township |
Summer 2023 |
Summer 2023 |
Card Road |
Hall Road (M-59) to 350 feet north |
$204,129 |
Construct Dual Right Turn Lanes |
Macomb Township |
Summer 2023 |
Summer 2023 |
Coon Creek Road Bridge |
Coon Creek Road to 100 feet north of Armada Ridge Road |
$1,038,553 |
Bridge Replacement |
Armada Township |
Summer 2023 |
Fall 2023 |
Garfield Road |
22 Mile Road to 23 Mile Road |
$4,579,947 |
Construct New Road |
Macomb Township |
Spring 2023 |
Fall 2023 |
Kelly Road |
14 Mile Road to 15 Mile Road |
$4,450,000 |
Reconstruction |
Clinton Township and Fraser |
Summer 2023 |
Fall 2023 |
Metropolitan Parkway (16 Mile Road) |
Ryan Road to Mound Road |
$4,071,808 |
Mill, Base Repair, and Asphalt Overlay |
Sterling Heights |
Summer 2023 |
Fall 2023 |
Mound Road |
I-696 to M-59 |
$80,000,000 |
Reconstruction |
Sterling Heights and Warren |
Summer 2021 |
Spring 2024 |
North Bay Drive, Precision Drive, and Commerce Boulevard |
25 Mile Road to 26 Mile Road |
$5,454,379 |
Reconstruction |
Chesterfield Township |
Spring 2023 |
Summer 2023 |
Schoenherr Road |
19 Mile Road to Hall Road (M-59) |
$3,509,946 |
Mill, Base Repair, and Asphalt Overlay |
Sterling Heights |
Spring 2023 |
Summer 2023 |
Washington Road Bridge |
Over the Salt River |
$4,402,705 |
Bridge Replacement |
Chesterfield Township |
Summer 2023 |
Fall 2023 |
West Archer Drive |
Over Channel to Lake St. Clair |
$2,333,209 |
Bridge Replacement |
Harrison Township |
Summer 2023 |
Fall 2023 |
Wolcott Road |
Over Tupper Brook Drain |
$383,000 |
Culver Replacement |
Armada Township |
Spring 2023 |
Summer 2023 |
Asphalt Pavement Preservation Program |
Multiple Locations |
$3,000,000 |
Repairs on Various Roads within the County |
Various Locations |
Spring 2023 |
Fall 2023 |
Concrete Pavement Preservation Program |
Multiple Locations |
$3,000,000 |
Repairs on Various Roads within the County |
Various Locations |
Spring 2023 |
Fall 2023 |
Subdivision Reconstruction Program |
Multiple Locations |
$3,593,212 |
Reconstruction |
Various Locations |
Summer 2023 |
Fall 2023 |
Fiber Phase 3 |
Multiple Locations |
$2,539,625.76 |
Install Fiber Optic Cable on Various Roads within Macomb County |
Various Locations |
February 2022 |
December 2024 |
Signal Modernization |
Multiple Locations |
$1,032,611.89 |
Upgrade Existing Diagonal Span Configuration to Box Span Configuration |
Various Locations |
November 2021 |
July 2023 |
Fiber Phase 4 |
Multiple Locations |
$2,373,076.86 |
Install Fiber Optic Cable on Various Roads within Macomb County |
Various Locations |
November 2023 |
July 2025 |
Longitudinal Pavement Marking |
Multiple Locations |
$590,000.00 |
Application of Longitudinal Pavement Markings |
Various Locations |
Spring 2023 |
Spring 2024 |
Special Pavement Marking |
Multiple Locations |
$180,000.00 |
Upgrade Stop Bars and Crosswalks |
Various Locations |
Spring 2023 |
Spring 2024 |
Guardrail Safety |
Multiple Locations |
$235,000.00 |
Upgrade Guardrails |
Various Locations |
Spring 2023 |
Spring 2024 |
Signal Modernization |
Multiple Locations |
$1,333,222.00 |
Upgrade Existing Diagonal Span Configuration to Box Span Configuration |
Various Locations |
Summer 2023 |
Spring 2025 |
Storm Water Pump Stations Rehabilitation |
Multiple Locations |
$400,000.00 |
Storm Water Mechanical and Electrical Systems Replacement |
Harrison Township |
Summer 2023 |
Fall 2024 |
Traffic Operations Center Operations |
County Wide |
$3,665,000.00 |
Operation and Maintenance of the Macomb County Traffic Operations Center |
Various Locations |
Winter 2023 |
Winter 2024 |
Fiber Phase 5 |
Multiple Locations |
$2,383,503.00 |
Install Fiber Optic Cable on Various Roads within Macomb County |
Various Locations |
Winter 2023 |
Summer 2026 |
For a comprehensive list of 2023 construction projects, maps, and information, visit roads.macombgov.org. Motorists can also sign up to receive email and text alerts for construction and traffic updates at roads.macombgov.org.